Hydrotite CJ-1020-2K / CJ-0725-3K
A highly sophisticated hydrophilic waterstop

Hydrotite is a Japanese brand name for a state-of-the-art hydrophilic waterstop with unmatched durability and water sealing capacity.

It is 100% made in Japan and is engineered to stay firm and intact under repeated and prolonged wet-dry cycling.

  • Hydrotite CJ-1020-2K and Hydrotite CJ-0725-3K are designed for sealing construction joints internally in cast-in-situ concrete where limited access restricts the use of conventional waterstops.

  • The waterstop is unique in the market in sense that it is a combination of (expanding) hydrophilic materials and (non-expanding) chloroprene rubber co-extruded together to form a single preformed strip.

    • The hydrophilic materials are engineered with the controlled expansion properties.  This controlled expansion means that it will neither cause spalling in structure nor let the waterstop be expanded to a point at which itself get destroyed.

    • The hydrophilic materials will gradually expand in the presence of moisture and will return to its original size if there is no more water or moisture present.  It will then re-expand when water or moisture is again introduced to the joint.  This repeated wet-dry cycling will not affect the functioning of the waterstop.

    • Noted for its long-term durability, the chloroprene serves to reinforce the hydrophilic materials to make it firm. The hollow core design can absorb some of the expansion pressure and thus prevent concrete from cracking due to high expansion pressure.

  • The waterstop is free from bentonite.

  • The waterstop is treated with a delay coating that serves to delay premature expansion by rain or ground water during installation, and water from freshly poured concrete during the curing process.

  • The waterstop has a service life of 120 years.

  • The waterstop can support 150m heads of water.

  • The waterstop meets BS 6920 requirement for use in contact with potable water (WRAS approved).

  • Hydrotite CJ-1020-2K can fulfill the requirement of G.S. Clause 21.2.20 and MTR M&W Specification Clause 8.1.

 

Both CJ-1020-2K and CJ-0725-3K are ex-stock Hong Kong for quick delivery to meet your construction schedule.

未命名_edited.jpg
IMG_20240320_113641_421_edited_edited_ed

Hydrotite CJ-1020-2K / CJ-0725-3K has a proven track record in Hong Kong.  There were already applications in Hong Kong before the handover of the city to the Motherland.  The waterstops' job references are namely but not limited to: -

  • Highways Department (HyD) Contract No. HY/2014/20 - Central Kowloon Route - Yau Ma Tei West

  • Drainage Services Department (DSD) Contract No. DC/2019/07 - Outlying Islands Sewerage, Stage 2 - Upgrading of Cheung Chau Sewage Treatment & Disposal Facilities

  • HyD Contract No. HY/2019/13 - Central Kowloon Route - Buildings, Electrical & Mechanical Works

  • Airport Authority Hong Kong (AAHK) Contract No. 3310 - Three Runway System Project - North Runway Modification Works

  • HyD Contract No. HY/2014/07 - Central Kowloon Route - Kai Tak West

  • HyD Contract No. HY/2018/02 - Central Kowloon Route - Kai Tak East
  • AAHK Contract No. 3408 - Three Runway System Project - Third Runway Concourse & Apron Works

  • Hospital Authority (HA) Contract No. HAHO(S)/T/21-S024 - Main Works Package 2 - Superstructure & Associated Works for Redevelopment of Grantham Hospital (Phase 1)

  • Water Supplies Department (WSD) Contract No. 1/WSD/19 - In-situ Reprovisioning of Sha Tin Water Treatment Works (South Works) - Water Treatment Works & Ancillary Facilities

  • Hong Kong Housing Authority (HKHA) Contract No. 20170567 - Construction of Public Housing Development at Hiu Ming Street (Combined Recreational Facilities Reprovision, Site Formation, Foundation & Building Contract)

  • Civil Engineering & Development Department (CEDD) Contract No. ED/2018/05 - Kai Tak Development - Stage 5B Infrastructure Works at the Former North Apron Area

  • HyD Contract No. HY/2014/08 - Central Kowloon Route - Yau Ma Tei East

  • WSD Contract No. 7/WSD/21 - Construction of Siu Ho Wan Water Treatment Works Extension & Siu Ho Wan Raw Water Booster Pumping Station

  • WSD Contract No. 21/WSD/21 - Relocation of Diamond Hill Fresh Water and Salt Water Service Reservoirs to Caverns

  • Residential Development at Various Lots in DD 374 & DD 375 & Adjacent Government Land, So Kwun Wat, Area 56, Tuen Mun for Sun Hung Kai Properties (SHKP) & Hanison

  • MTR Corporation (MTR) Tung Chung Line Extension Contract No. 1202: Tung Chung East Station & Associated Enabling Works for Track Diversions

  • CEDD Contract No. CV/2020/02 - Construction of Subway in Support of the Provision of Columbarium at Shek Mun

  • CEDD Contract No. NL/2020/02 - Tung Chung New Town Extension - Salt Water Supply System

  • CEDD Contract No. NL/2020/07 - Tung Chung New Town Extension - Tai Ho Interchange

  • HyD Contract No. HY/2022/15 - Provision of Universal Accessibility Facilities at Footbridges, Elevated Walkways & Subways - Package 5 Contract 3

  • DSD Contract No. DC/2018/09 - Rehabilitation of Trunk Sewers in Tuen Mun

  • CEDD Contract No. CV/2019/03 - Site Formation & Infrastructure Works at Pik Wan Road, Yau Tong

  • CEDD Contract No. CV/2018/03 - Site Formation & Infrastructure Works at Wang Chau, Yuen Long - Contract 2

  • HyD Contract No. HY/2018/12 - Provision of Universal Accessibility Facilities at Footbridges, Elevated Walkways & Subways - Package 4 Contract 1

  • Comprehensive Development at TSWTL 23, Planning Area 33, Tin Shui Wai (YOHO West) for MTR & SHKP

  • Architectural Services Department (ArchSD) Contract No. TC K972 - Term Contract for the Design & Construction of Minor Works to Government & Subvented Properties for which the Architectural Services Department is Responsible [Contract Area: Kowloon & Outlying Islands (Sai Kung)]

  • Residential Development at TMTL 483, Siu Hong, Area 54, Tuen Mun (Novo Land) for SHKP

  • HKHA Contract No. 20200312 - Construction of Public Housing Development at Hin Fat Lane, Tuen Mun

  • CEDD Contract No. YL/2020/02 - Development of Lok Ma Chau Loop: Main Works Package 1 - Contract 2 Western Connection Road Phase 2, Connection Roads to Fanling / San Tin Highway & Direct Road Link Phase 1

  • Composite Building at KIL 11240 at J/O Soy Street & Shanghai Street, Mong Kok

  • AAHK Contract No. 3302 - Three Runway System Project - Eastern Vehicular Tunnel Advance Works

  • Environmental Protection Department (EPD) Contract No. EP/SP/86/15 - Organic Waste Treatment Facilities Phase 2

  • AAHK Contract No. 3801 - Three Runway System Project - APM & BHS Tunnels on Existing Airport Island

  • Residential Development at TPTL 244, J/O Yau King Lane & Pok Yin Road, Pak Shek Kok, Tai Po (Silicon Hill) for SHKP

  • WSD Contract No. 3/WSD/18 - Construction of Tong Hang No. 3 Fresh Water Service Reservoir & Associated Mainlaying

  • CEDD Contract No. ND/2018/01 - Site Formation & Infrastructure Works for Police Facilities in Kong Nga Po

  • CEDD Contract No. NE/2015/01 - Tseung Kwan O-Lam Tin Tunnel - Main Tunnel and Associated Works

  • CEDD Contract No. KL/2014/01 - Kai Tak Development - Stage 2 Infrastructure Works for Developments at the Southern Part of the Former Runway

  • Residential Development at YTIL 44, 18 Shung Shun Street, Yau Tong (Montego Bay) for Minmetals Land

  • DSD Contract No. DC/2020/07 - Village Sewerage in Northern Tuen Mun

  • CEDD Contract No. CV/2017/07 - Site Formation & Infrastructure Works at Wang Chau, Yuen Long - Contract 1

  • HKHA Contract No. 20180305 - Construction of Subsidized Sale Flats Development at Tung Chung Area 54

  • CEDD Contract No. YL/2020/01 - Development of Lok Ma Chau Loop: Main Works Package 1 - Contract 1 Site Formation & Infrastructure Works inside Lok Ma Chau Loop & Western Connection Road Phase 1

  • WSD Contract No. 5/WSD/19 - Improvement to Dongjiang Water Mains P4 at Sheung Shui & Fanling

  • Comprehensive Development at TMTL 463, Siu Sau, Area 55, Tuen Mun (Grand Jeté) for SHKP & Cheung Kong

  • CEDD Contract No. CV/2019/04 - Site Formation & Infrastructure Works near Tsz Tin Road & Hing Fu Street in Area 54, Tuen Mun

  • DSD Contract No. DC/2017/05 - Enhancement Works for Kwun Tong Sewage Pumping Station

  • WSD Contract No. 2/WSD/20 - Construction of Sheung Wong Yi Au No. 3 Fresh Water Service Reservoir

  • CEDD Contract No. CV/2020/01 - Site Formation & Infrastructure Works for Public Housing Developments at Pok Fu Lam South

  • AAHK Contract No. 3405 - Three Runway System Project - Third Runway Concourse Foundation & Substructure Works

  • DSD Contract No. DC/2017/01 - Construction of Dry Weather Flow Interceptor at Cherry Street Box Culvert

  • CEDD Contract No. ND/2019/01 - Kwu Tung North New Development Area, Phase 1: Site Formation & Infrastructure Works

  • HKHA Contract No. 20210293 - Construction of Public Housing Development at Anderson Road Quarry Site R2-5

  • DSD Contract No. DC/2018/08 - Inter-Reservoirs Transfer Scheme - Water Tunnel between Kowloon Byewash Reservoir & Lower Shing Mun Reservoir

(The list continued below)

  • CK Center Phase II, 10 Harcourt Road, Central for Hutchison Whampoa

  • CEDD Contract No. YL/2017/01 - Site Formation & Infrastructure Works for Development at Kam Tin South, Yuen Long - Advance Works

  • DSD Contract No. DC/2019/11 - Upgrading of West Kowloon & Tsuen Wan Sewerage - Phase 2A

  • HyD Contract No. HY/2018/11 - Provision of Universal Accessibility Facilities at Footbridges, Elevated Walkways & Subways - Package 3 Contract 1

  • AAHK Contract No. C18W02 - H.K. Int’l Airport - Intermodal Transfer Terminal Building

  • Residential Development at 28 Old Bailey Street, Mid-Level for Emperor

  • AAHK Contract No. C18W07 - H.K. Int’l Airport - Office Tower Development

  • DSD Contract No. DC/2018/04 - Sewerage at Lei Yue Mun Village

  • CEDD Contract No. YL/2019/02 - Hung Shui Kiu/Ha Tsuen New Development Area Advance Works Phase 2 - Site Formation & Engineering Infrastructure

  • HKHA Contract No. 20150547 - Construction of Public Housing Developments at North West Kowloon Reclamation Site 6 & Fat Tseung Street West

  • CEDD Contract No. CV/2019/02 - Reconstruction of Pak Kok Pier on Lamma Island

  • HyD Contract No. HY/2020/24 - Provision of Universal Accessibility Facilities at Footbridges, Elevated Walkways & Subways - Package 5 Contract 1

  • Urban Renewal Authority (URA) Reclamation Street/Shantung Street Project (YTM-010) at KIL 11254, Mong Kok (One Soho) for Sino Land & Chuang’s

  • ArchSD Contract No. SS G504 - Construction of a Government Data Centre Complex at King Lam Street, Cheung Sha Wan

  • WSD Contract No. 7/WSD/16 - Uprating of Chai Wan Salt Water Supply System - Mainlaying & Upgrading of Siu Sai Wan Salt Water Pumping Station

  • ArchSD Contract No. RF G508 - Conversion of Secondary Pool & Children's Pool for the Provision of Heated Pool at Morse Park Swimming Pool Complex

  • MTR Wong Chuk Hang Station Package 4 Property Development at AIL 467, Site D for Kerry, Swire & Sino Land

  • Residential Redevelopment at RBL 801, 3 South Bay Close, Repulse Bay

  • DSD Contract No. DC/2018/11 - Upgrading of Central & East Kowloon Sewerage - Phase 3

  • CEDD Contract No. ND/2019/05 - Fanling North New Development Area, Phase 1: Fanling Bypass Eastern Section (Shung Him Tong to Kau Lung Hang)

  • ArchSD Contract No. SS J521 - Lei Yue Mun Waterfront Enhancement Project (Phase 1)

  • EPD Contract No. EP/SP/66/12 - Integrated Waste Management Facilities Phase 1

  • DSD Contract No. DC/2013/10 - Design, Build & Operate San Wai Sewage Treatment Works - Phase 1

  • Academic Building for St. Stephen's College, 22 Tung Tau Wan Road, Stanley

  • ArchSD Contract No. SS E510 - Construction of the East Kowloon Cultural Centre in Kowloon Bay

  • HyD Contract No. HY/2019/01 - H.K.-Zhuhai-Macao Bridge H.K. Boundary Crossing Facilities - Phase 2 & Other Works

  • CEDD Contract No. YL/2017/03 - Development of Lok Ma Chau Loop: Land Decontamination & Advance Engineering Works

  • ArchSD Contract No. SS G503 - Reprovisioning of Fu Shan Public Mortuary at Sha Tin

  • AAHK Contract No. C19W15 - H.K. Int’l Airport - HKIA Tower Refurbishment Works

  • Subcontract for the Engineering, Procurement & Construction of SENT Landfill Extension (SENTX) for Green Valley Landfill

  • Residential Development at 233-235 Prince Edward Road West, Ho Man Tin for SHKP & Wheelock

  • Commercial Development at Site A2 (L894) & Site A3 (L923) of SKYCITY at CLKL 3 at H.K. Int’l Airport (11 SKIES) for New World

  • HKHA Contract No. 20190090 - Construction of Subsidised Sale Flats Development at Diamond Hill Comprehensive Development Area

  • WSD Contract No. 4/WSD/17 - Construction of Tung Chung No. 2 Fresh Water Service Reservoir

  • Commercial Accommodation & Associated Facilities (CAAF) for MTR Wong Chuk Hang Station, Package Three Property Development at AIL 467, Site C for Cheung Kong

  • DSD Contract No. DC/2016/01 - Construction of an Additional Sewage Rising Main between Tung Chung & Siu Ho Wan & Associated Works

  • Residential Development at Site H & Estate Roads of TKOTL 70 RP, Lohas Park Package 8 (Sea to Sky) for MTR & Cheung Kong

  • HyD Contract No. HY/2018/09 - Lift & Pedestrian Walkway System between Tai Wo Hau Road & Wo Tong Tsui Street, Kwai Chung

  • DSD Contract No. DC/2018/02 - Upgrading of Sewage Pumping Stations & Sewerage along Ting Kok Road

  • Main Contract Works at Central Market, Central by URA

  • MTR Shatin to Central Link Contract No. 1121: NSL Cross Harbour Tunnels

  • Residential Development at Lot 1068 in SD 3 off Anderson Road, Kwun Tong (Mount Anderson) for Chinachem

  • Residential Development at YLTL 461, 21 Wang Yip Street West, Yuen Long (After The Rain)

  • ArchSD Contract No. SS G509 - Signature Project Scheme (Wan Chai District) - Construction of Moreton Terrace Activities Centre

  • Composite Redevelopment at KIL 7779, 107-111 Tung Chau Street, Tai Kok Tsui (The Cloud)

  • CEDD Contract No. KL/2015/02 - Kai Tak Development - Stage 5A Infrastructure at Former North Apron Area

  • Chung Chi Student Development Complex at Chung Chi College for Chinese University of Hong Kong

  • CEDD Contract No. NL/2017/01 - Infrastructure Works for Public Housing Development at Area 54, Tung Chung

  • ArchSD Contract No. SS G506 - Construction of Station Square at Kai Tak (Phase 1)

  • Industrial Development at Lot 313 & TWIL 49, Tsuen Wan for Goodman Asia

  • Residential Development at Lot 1066 in DD 103, 3 Ko Po Path, Au Tau, Yuen Long (Crescent Green) for Road King Infrastructure

  • Redevelopment of Conservation Building at Kadoorie Farm & Botanic Garden, Tai Po

  • Hotel Development at NKIL 6550 off Hing Wah Street West, Cheung Sha Wan (Townplace West Kowloon) for SHKP

  • Residential Development at TPTL 223 & TPTL 229, 36 Lo Fai Road, Tai Po (Villa Lucca) for Hysan & HKR International

  • ArchSD Contract No. SS G514 - Construction of Two 30-classroom Primary Schools at Queen's Hill, Fanling

  • WSD Contract No. 3/WSD/15 - In-situ Reprovisioning of Sha Tin Water Treatment Works (South Works) - Advance Works

  • WSD Contract No. 4/WSD/16 - Improvement of Water Supply to Sheung Shui & Fanling

  • ArchSD Contract No. SS E511 - Reprovisioning of Shanghai Street Refuse Collection Point & Street Sleepers' Services Units to the Site on Hau Cheung Street, Yau Ma Tei

  • MTR Shatin to Central Link Contract No. 1112: Hung Hom Station & Stabling Sidings

  • Residential Development at FSSTL 262, Ma Sik Road, Area 18, Fanling by Henderson

  • HyD Contract No. HY/2012/08 - Tuen Mun-Chek Lap Kok Link - Northern Connection Sub-Sea Tunnel Section

  • The Hopewell Centre II Project at IL 8715, Ship Street & Kennedy Road, Wan Chai

  • Commercial Development at 28-32 Stanley Street, Central

  • HyD Contract No. HY/2013/17 - Road Improvement Works in West Kowloon Reclamation Development

  • CEDD Contract No. CV/2012/05 - Bathing Beach at Lung Mei, Tai Po

  • HyD Contract No. HY/2013/12 - Tuen Mun-Chek Lap Kok Link - Northern Connection Toll Plaza & Associated Works

  • HyD Contract No. HY/2014/09 - Central Kowloon Route - Ho Man Tin Access Shaft

  • CEDD Contract No. KL/2014/03 - Kai Tak Development - Stage 3 Infrastructure Works for Developments at the Southern Part of the Former Runway

  • HyD Contract No. HY/2015/06 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 3 Contract 8

  • CEDD Contract No. NE/2015/03 - Tseung Kwan O-Lam Tin Tunnel - Northern Footbridge

  • House Development at Lot 1681 in DD 243, J/O Pik Sha Road & Clear Water Bay Road, Sai Kung

  • CEDD Contract No. CV/2013/08 - Liantang/Heung Yuen Wai Boundary Control Point Site Formation & Infrastructure Works - Contract 6

  • Residential Development at 8-10A Mosque Street, Mid-Levels (Central 8) for Emperor

  • DSD Contract No. DC/2011/04 - Reconstruction, Improvement & Rehabilitation of Kai Tak River from Wong Tai Sin Police Station to Tung Tau II Estate

  • DSD Contract No. DC/2014/01 - Castle Peak Road Trunk Sewer & Tuen Mun Village Sewerage

  • AAHK Contract No. P575 - H.K. Int’l Airport - NCD Main Infrastructure Works

  • House Development at RBL 169 RP, 29A Lugard Road, The Peak by Henderson

  • CEDD Contract No. CV/2014/02 - Provision of Universal Access Facilities for Highway Structures - Package 2 Contract 1

  • AAHK Contract No. 3501 - Three Runway System Project - Antenna Farm & Sewage Pumping Station

  • Footbridge Extension across Nathan Road for SHKP

  • HyD Contract No. HY/2014/06 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 3 Contract 5

  • MTR Shatin to Central Link Contract No. 1106: Diamond Hill Station & Diamond Hill Stabling Sidings

  • DSD Contract No. DC/2009/10 - HATS Stage 2A - Upgrading Works at Stonecutters Island Sewage Treatment Works - Main Pumping Station, Sedimentation Tanks & Ancillary Facilities

  • HyD Contract No. HY/2014/12 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 3 Contract 6

  • URA Hai Tan Street/Kweilin Street & Pei Ho Street Development (SSP/1/003-005) at NKIL 6506, Sham Shui Po (Seaside Sonata) for Cheung Kong

  • Residential Redevelopment at RBL 670 RP, 75 Peak Road, The Peak

  • Hong Kong Disneyland Resort Project GC-29 - Sleeping Beauty Castle & Hub

  • CEDD Contract No. CV/2016/06 - Widening of Footbridge Connecting Pak Wo Road to MTR Fanling Station & its Associated Works

  • CEDD Contract No. KL/2015/03 - Kai Tak Development - Stage 3B Infrastructure at Former North Apron Area

  • AAHK Contract No. P581 - H.K. Int’l Airport - East Hall Expansion Works

  • MTR Shatin to Central Link Contract No. 1124: Admiralty SCL Related Works

  • Comprehensive Development at TSWTL 34, 9 Wetland Park Road, Area 115, Tin Shui Wai (Wetland Seasons Park) for SHKP

  • MTR West Rail Yuen Long Station Property Development at YLTL 510, Yuen Long for SHKP

  • ArchSD Contract No. SS A501 - Design & Construction of Hong Kong Children’s Hospital

  • CEDD Contract No. HK/2009/02 - Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai East

  • CEDD Contract No. KL/2016/01 - West Kowloon Reclamation - Main Works (Remainder) - Footbridge at J/O Sham Mong Road & Tonkin Street West in Sham Shui Po

  • Happy Valley Clubhouse Extension at 25 Shan Kwong Road, Happy Valley for the Hong Kong Jockey Club

  • HyD Contract No. HY/2013/01 - H.K.-Zhuhai-Macao Bridge H.K. Boundary Crossing Facilities - Passenger Clearance Building

  • Contract No. GW/2015/05/038 - Public Infrastructure Works for Phase I Development of West Kowloon Cultural District (Package 1) for West Kowloon Cultural District Authority (WKCDA)

  • CEDD Contract No. HK/2012/08 - Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai West

  • CEDD Contract No. KL/2011/01 - Kai Tak Development - Reconstruction & Upgrading of Kai Tak Nullah

  • Composite Development at 165-167 Nam Cheong Street, Shum Shui Po

  • HyD Contract No. HY/2014/18 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 3 Contract 7

  • CEDD Contract No. CV/2015/08 - Provision of Universal Access Facilities for Highway Structures - Package 1 Contract 3

  • DSD Contract No. DC/2013/01 - Tolo Harbour Sewerage of Unsewered Areas Stage 2 - Phase 1 & Sewerage in Nam Wa Po & Wai Tau

  • HKHA Contract No. 20150624 - Foundation for Public Rental Housing Development Phase 1 at Diamond Hill Comprehensive Development Area, Wong Tai Sin

  • HyD Contract No. HY/2011/03 - H.K.-Zhuhai-Macao Bridge H.K. Link Road - Section between Scenic Hill & H.K. Boundary Crossing Facilities

  • HyD Contract No. HY/2013/03 - H.K.-Zhuhai-Macao Bridge H.K. Boundary Crossing Facilities - Vehicle Clearance Plazas & Ancillary Buildings & Facilities

  • New World Centre Remodeling Project at KIL 9844, 18-24 Salisbury Road, Tsim Sha Tsui (Victoria Dockside) for New World

  • CEDD Contract No. CV/2015/02 - Provision of Universal Access Facilities for Highway Structures - Package 2 Contract 2

  • CEDD Contract No. CV/2015/01 - Provision of Universal Access Facilities for Highway Structures - Package 1 Contract 2

  • CEDD Contract No. CV/2014/03 - Provision of Universal Access Facilities for Highway Structures - Package 1 Contract 1

  • MTR South Island Line (East) Contract No. 914: External Works in Harcourt Garden, Admiralty

  • WSD Contract No. 15/WSD/10 - Expansion of Tai Po Water Treatment Works & Ancillary Raw Water & Fresh Water Transfer Facilities - Design & Build of New Stream II

  • HyD Contract No. HY/2010/08 - Central-Wan Chai Bypass - Tunnel (Slip Road 8 Section)

  • HyD Contract No. HY/2013/02 - H.K.-Zhuhai-Macao Bridge H.K. Boundary Crossing Facilities - Infrastructure Works Stage I (Western Portion)

  • Phase 2 Development at MTR West Rail Tsuen Wan West Station (TW5) Bayside, TWTL 401, Tsuen Wan (Ocean Supreme) by Cheung Kong

  • AAHK Contract No. P561 - H.K. Int’l Airport - North Commercial District Enabling Works

  • MTR Shatin to Central Link Contract No. 1102: Hin Keng Station & Approach Structures

  • MTR Shatin to Central Link Contract No. 1123: Exhibition Station & Western Approach Tunnel

  • DSD Contract No. DC/2009/24 - HATS Stage 2A - Upgrading of Preliminary Treatment Works at Sandy Bay, Cyberport, Wah Fu, Aberdeen & Ap Lei Chau

  • CEDD Contract No. KL/2012/03 - Kai Tak Development - Stage 4 Infrastructure at Former North Apron Area

  • HyD Contract No. HY/2013/15 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 3 Contract 3

  • Contract No. CC/2016/3B/045 - Main Contract for The Park for West Kowloon Cultural District Authority

  • AAHK Contract No. P573 - H.K. Int’l Airport - NCD Advance Infrastructure Works

  • MTR Shatin to Central Link Contract No. 1111: Hung Hom North Approach Tunnels

  • ArchSD Contract No. SS D505 - Reprovisioning of FEHD Sai Yee Street Environmental Hygiene Offices-cum-Vehicle Depot at Yen Ming Road, West Kowloon Reclamation Area

  • CEDD Contract No. NE/2014/05 - Ma On Shan Development - Roads, Drainage & Sewerage Works at Whitehead & Lok Wo Sha, Phase 2

  • DSD Contract No. DC/2013/09 - Shek Wu Hui Sewage Treatment Works - Further Expansion Phase 1A - Advance Works

  • HyD Contract No. HY/2013/04 - H.K.-Zhuhai-Macao Bridge H.K. Boundary Crossing Facilities - Infrastructure Works Stage II (Southern Portion)

  • Industrial Development at 43-45 Tsun Yip Street, Kwun Tong (CORE45) for New World

  • DSD Contract No. DC/2012/02 - Upgrading of Mui Wo Sewage Treatment Works & Village Sewerage at Wang Tong & Yue Kwong Chuen

  • DSD Contract No. DC/2013/04 - Outlying Islands Sewerage, Stage 2 - Lamma Village Sewerage Phase 2, Package 1

  • CEDD Contract No. CV/2016/02 - Road & Infrastructure Works for Development at Lin Cheung Road, Sham Shui Po

  • Commercial Redevelopment at 704-730 King's Road, North Point (K11 ATELIER King's Road) for New World

  • HyD Contract No. HY/2013/11 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 3 Contract 2

  • MTR Contract No. K1434-14C: Station Improvement Works at KOT

  • WSD Contract No. 4/WSD/11 - Construction of Butterfly Valley Fresh Water Primary Service Reservoir Extension & Associated Mainlaying

  • House Redevelopment at 46 Fuk Lo Tsun Road, Kowloon City

  • MTR Express Rail Link Contract No. 825: Mai Po to Ngau Tam Mei Tunnels

  • DSD Contract No. DC/2012/03 - Happy Valley Underground Stormwater Storage Scheme

  • HA Contract No. 8110030604 - Foundation & Associated Works Contract for Main Works Package 1 for Expansion of United Christian Hospital

  • ArchSD Contract No. SS D502 - Design & Construction of Kwun Tong Staff Quarters at 4 Tseung Kwan O Road, Kowloon

  • MTR Shatin to Central Link Contract No. 1108: Kai Tak Station & Associated Tunnels

  • Commercial Development at KTIL 761, 348 Kwun Tong Road, Kowloon East (Mapletree Bay Point) for Mapletree

  • MTR Shatin to Central Link Contract No. 1126: Reprovisioning of Harbour Road Sports Centre & Wan Chai Swimming Pool

  • MTR Contract No. C6593-13C: Lee Tung Street Subway at Wan Chai Station

  • Development at Area 1A/1B of Lot 385 RP & Exts in DD 352, Discovery Bay for HKR International

  • HKHA Contract No. 20130521 - Construction of Public Rental Housing Development at Tuen Mun Area 54 Site 2 Phases 1 & 2

  • MTR Express Rail Link Contract No. 824: Ngau Tam Mei to Tai Kong Po Tunnels

  • Residential Development at SIL 854, 1 Oi Tak Street, Shau Kei Wan (Lanson Place) for Wing Tai

  • Construction of New Annex at PLK Laws Foundation College at 8 To Lok Road, Tseung Kwan O

  • HyD Contract No. HY/2012/12 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 2

  • HyD Contract No. HY/2013/23 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 3 Contract 4

  • Residential & Commercial Development at 420-422 Prince Edward Road West, Kowloon City for Chow Tai Fook

  • HyD Contract No. HY/2013/16 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 2 Contract 2

  • New Campus of Technological & Higher Education Institute of Hong Kong (THEi) at CWIL 182, J/O Shing Tai Road & Wing Tai Road, Chai Wan for VTC

  • CLP Contract No. 450080607 - Design & Construction of Kai Tak Cable Tunnel

  • MTR Shatin to Central Link Contract No. 1107: Diamond Hill to Kai Tak Tunnels

  • AAHK Contract No. M788-5 - H.K. Int’l Airport - Construction of Temporary Parking Area for Business Jets

  • MTR South Island Line (East) Contract No. 902: Nam Fung Tunnel & Ventilation Buildings.

  • HKHA Contract No. 20140235 - Foundation for Public Rental Housing Development at Shek Kip Mei Estate Phase 6

  • MTR Express Rail Link Contract No. 823A: Tai Kong Po to Tse Uk Tsuen Tunnels

  • CEDD Contract No. CV/2013/03 - Liantang/Heung Yuen Wai Boundary Control Point Site Formation & Infrastructure Works - Contract 5

  • CEDD Contract No. CV/2012/02 - Construction of Sewage Pumping Station near Tsz Tin Road & Associated Sewerage Works in Area 54, Tuen Mun

  • MTR Express Rail Link Contract No. 823B: Shek Kong Stabling Sidings & Emergency Rescue Sidings

  • HyD Contract No. HY/2012/07 - Tuen Mun-Chek Lap Kok Link - Southern Connection Viaduct Section

  • HyD Contract No. HY/2010/02 - H.K.-Zhuhai-Macao Bridge H.K. Boundary Crossing Facilities - Reclamation

  • HyD Contract No. HY/2012/11 - Provision of Barrier-free Access Facilities for Highway Structures - Phase 3 Contract 1

  • Hostel Development at Lot 279 in DD 335, South Lantau Road, Pui O (Swire Leadership Centre) for Swire

  • Redevelopment of Block X, The Hong Kong Polytechnic University

  • Urban Renewal Project (K28) at KIL 11212, 17 Nelson Street, Mongkok (Skypark) for URA & New World

  • CEDD Contract No. HK/2009/01 - Wan Chai Development Phase II - Central-Wan Chai Bypass at Hong Kong Convention & Exhibition Centre

  • Composite Redevelopment at 321 Des Voeux Road West, Sai Wan (Bohemian House) for New World & Henderson

  • MTR Contract No. C6591-13C: Provision of Lift Shaft at YMT Station

  • Residential Development at IL 5749 RP, 44 Stubbs Road, Mid-Level (Harmony)

  • MTR Kwun Tong Line Extension Contract No. 1001: Yau Ma Tei to Whampoa Tunnels & Ho Man Tin Station

  • MGM Cotai Project

  • Residential Redevelopment at 23 & 25 Robinson Road, Mid-Level (Wellesley) for Henderson

  • MTR South Island Line (East) Contract No. 901: Admiralty Integrated Station & SCL Enabling Works

  • MTR Shatin to Central Link Contract No. 1109: Sung Wong Toi & To Kwa Wan Stations & Tunnels

  • MTR West Island Line Contract No. 704: Sai Ying Pun & Hong Kong University Station, & Sai Ying Pun to Kennedy Town Tunnel Construction

  • Central Police Station Conservation & Revitalisation Project

  • Hotel Development at 8-12A Ha Heung Road, To Kwa Wan (iclub To Kwa Wan Hotel) for Paliburg & Regal

  • Building Conversion at 8 Wang Kwong Road, Kowloon Bay (Mega Cube) for Henderson

  • WSD Contract No. 5/WSD/14 - Mainlaying at Lan Nai Wan & Magazine Gap, & Construction of Fresh Water Tank at Sham Tseng & Annex Building at Telegraph Bay Fresh Water Pumping Station

  • MTR South Island Line (East) Contract No. 904: Lei Tung Station, South Horizons Station & Tunnels

  • CEDD Contract No. CV/2007/03 - Development at Anderson Road - Site Formation & Associated Infrastructure Works

  • MTR West Rail Long Ping Station (South) Property Development at YLTL 512, Yuen Long (Sol City) for Chinachem

  • Residential Development at Lot 898 in DD 227, 663 Clear Water Bay Road, Tai Po Tsai, Sai Kung (Mount Pavilia) for New World

  • HKHA Contract No. 20130485 - Conversion of Chai Wan Factory Estate to Public Rental Housing

  • DSD Contract No. DC/2012/07 - Lam Tsuen Valley Sewerage - Village Sewerage, Stage 2, Phase 1

  • MTR Shatin to Central Link Contract No. 1117: Pat Heung Depot Modification Works

  • MTR South Island Line (East) Contract No. 903: Ocean Park Station, Wong Chuk Hang Station, Viaducts & Aberdeen Channel Bridge

  • New Campus Development of Chu Hai College of Higher Education at TMTL 489, Castle Peak Road, Tuen Mun

  • DSD Contract No. DC/2009/23 - HATS Stage 2A - Upgrading of Preliminary Treatment Works at North Point, Wan Chai East & Central

  • DSD Contract No. DC/2012/08 - Lam Tsuen Valley Sewerage - Village Sewerage, Stage 2, Phase 2

  • Residential Development at Lot 4309 in DD 124, 65-89 Tan Kwai Tsuen Road, Yuen Long (Casa Regalia & Domus) for Paliburg & Regal

  • Residential Development at 100 Caine Road, Mid-Levels (ALASSIO) for Swire

  • DSD Contract No. DC/2012/06 - Sewerage at Clear Water Bay Road, Pik Shui Sun Tsuen & West of Sai Kung Town

  • MTR Contract No. Q032314: Tsing Yi Town Lot 135 - TYLP Advance Works

  • Residential Development at STTL 562, 39-77 Lai Ping Road, Kau To (kau to HIGHLAND) for CSI

  • DSD Contract No. DC/2007/23 - HATS Stage 2A - Construction of Sewage Conveyance System from North Point to Stonecutters Island

  • MTR Contract No. C4680.C-11C: Provision of Lift Shafts at Lai Chi Kok, Sai Wan Ho & Prince Edward East Stations

  • HyD Contract No. HY/2008/11 - Reconstruction & Improvement of Tuen Mun Road - Sam Shing Hui Section

  • HyD Contract No. HY/2012/09 - Improvement of Kam Pok Road - Man Yuen Chuen Section & Proposed Vehicular Bridge across the Nullah at Kiu Hing Road near Wong Nai Tun

  • EMSD Contract No. 1020EM12A - District Cooling System at Kai Tak Development Phase III (Package A) - Chilled Water Pipe Laying Works

  • HyD Contract No. HY/2009/03 - Design & Build of Traffic Improvements to Tuen Mun Road Town Centre Section

  • HKHA Contract No. 20120604 - Foundation for Home Ownership Scheme Developments at Mei Mun Lane Shatin Area 4C, Pik Tin Street Shatin Area 4D & Hin Tin Street Shatin Area 31

  • DSD Contract No. DC/2009/14 - North District & Tolo Harbour Regional Sewerage - Upgrading of Sewage Pumping Stations & Trunk Sewers

  • Jockey Club Home for Hospice at STTL 5772, A Kung Kok Shan Road, Shatin

  • HyD Contract No. HY/2007/09 - Reconstruction & Improvement of Tuen Mun Road - Eastern Section

  • HyD Contract No. HY/2009/18 - Central-Wan Chai Bypass - Central Interchange

  • AAHK Contract No. P533 - H.K. Int’l Airport - Midfield Concourse & Terminal Building

  • DSD Contract No. DC/2009/11 - Tuen Mun Western Trunk Sewerage

  • Residential Development at HHIL 556, 9 Lee Kung Street, Hung Hom (La Lumière) for Cheung Kong

  • DSD Contract No. DC/2012/09 - Pak Hok Lam Trunk Sewer & Sha Tau Kok Village Sewerage

  • ArchSD Contract No. PI T330 - Construction of Piled Foundation & Caps for Public Library & Indoor Recreation Centre, Area 3, Yuen Long

  • HyD Contract No. HY/2009/19 - Central-Wan Chai Bypass - Tunnel (North Point Section) & Island Eastern Corridor Link

  • DSD Contract No. DC/2011/05 - Lam Tsuen Valley Sewerage - Village Sewerage, Stage 1

  • Commercial Development at 93-95 King's Road, North Point (KP Tower)

  • Revitalisation of the Old Tai Po Police Station into a Green Hub for Kadoorie Farm & Botanic Garden

  • Religious Building at TMTL 294 & Ext., Tsing Chung Koon Road, Tuen Mun (Ching Chung Taoist Association Building)

  • CEDD Contract No. CV/2012/07 - Development at Anderson Road - Footbridge D & Associated Works

  • DSD Contract No. DC/2010/06 - Upgrading of Central & East Kowloon Sewerage - Phase 2

  • DSD Contract No. DC/2010/02 - Drainage Improvement Works in Shuen Wan & Shek Wu Wai

  • Residential Development at FSSTL 177, 1 Ma Sik Road, Fanling (Green Code) for Henderson & Hong Kong Ferry

  • AAHK Contract No. P546 - H.K. Int’l Airport - Western Apron Expansion Works

  • EMSD Contract No. 1017EM10 - Design-Build-Operate a District Cooling System (Phase II Works) at Kai Tak Development

  • AAHK Contract No. P535 - H.K. Int’l Airport - West Hall Modification Works

  • DSD Contract No. DC/2009/09 - Construction of Tai Po Sewage Treatment Works, Stage 5 Phase 2B

  • Commercial Development at NKIL 6269, 83 Hoi Bun Road, Kwun Tong (One Bay East) for Wheelock

  • CEDD Contract No. IS/2010/01 - Construction of Riverwall at Yat Chung, Tai O & Ancillary Improvement Works

  • DSD Contract No. DC/2009/17 - HATS Stage 2A - Upgrading Works at Stonecutters Island Sewage Treatment Works - Sludge Dewatering Facilities

  • HKHA Contract No. 20100083 - Construction of Public Rental Housing Development at Tung Tau Cottage Area East

  • HyD Contract No. HY/2010/10 - Retrofitting of Noise Barriers on Tai Po Tai Wo Road near Po Nga Court

  • HyD Contract No. HY/2011/09 - H.K.-Zhuhai-Macao Bridge H.K. Link Road - Section between HKSAR Boundary & Scenic Hill

  • CEDD Contract No. YL/2012/01 - Widening of Tin Ha Road & Tan Kwai Tsuen Road

  • ArchSD Contract No. SS W304 - Design & Construction of Trade & Industry Tower in Kai Tak Development Area

  • HyD Contract No. HY/2007/10 - Reconstruction & Improvement of Tuen Mun Road - Tai Lam Section

  • DSD Contract No. DC/2009/22 - Drainage Improvement Works in Shuen Wan, Tai Po, Contract 1

  • Hong Kong Disneyland Resort Project GC-19 - Back of House Administration Building (TD2) - Enabling Works

  • TaiKoo Place Phase 2A Redevelopment at TaiKoo Place, Island East (One Taikoo Place) for Swire

  • DSD Contract No. DC/2009/21 - Provision of Interception Facilities at Jordan Valley Box Culvert (JVBC)

  • MTR West Island Line Contract No. 705: Kennedy Town Station & Overrun Tunnel Construction

  • ArchSD Contract No. SS W303 - Cruise Terminal Building & Ancillary Facilities for The Kai Tak Cruise Terminal Development

  • Residential Development at 55 Conduit Road, Mid-level for Chinese Estates & New World

  • HyD Contract No. HY/2008/12 - Bus-Bus Interchanges on Tuen Mun Road

  • HyD Contract No. HY/2009/17 - Central-Wan Chai Bypass - FEHD Whitfield Depot Re-provisioning Works

  • Residential Development at 211-215C Prince Edward Road West, Ho Man Tin (Kadoorie Hill) for Wheelock

  • Residential Redevelopment at NKIL 6498, 62 Begonia Road, Kowloon Tong for China Overseas

  • AAHK Contract No. P532 - H.K. Int’l Airport - Midfield Advanced Works

  • MTR Shatin to Central Link Contract No. 1115: New International Mail Centre

  • DSD Contract No. DC/2009/05 - HATS Stage 2A - Construction of the Interconnection Tunnel & Diaphragm Wall for Main Pumping Station at Stonecutters Island Sewage Treatment Works

  • DSD Contract No. DC/2008/03 - Design, Build & Operate Pillar Point Sewage Treatment Works

  • WSD Contract No. 8/WSD/11 - Construction of Pak Shek Kok Fresh Water Service Reservoir Extension

  • Residential Development at Lot 495 in DD 399, 380 Castle Peak Road, Casam Beach, Ting Kau (Deauville) for SHKP

  • EPD Contract No. EP/SP/58/08 - Design, Build & Operate Sludge Treatment Facilities

  • CEDD Contract No. CV/2011/01 - Site Formation & Infrastructural Works near Tsing Lun Road & Tsz Tin Road in Area 54, Tuen Mun

  • Residential Development at TMTL 449, Area 58, 8 Tsing Fat Lane, Siu Lam (Jade Grove) for Chinachem

  • CEDD Contract No. KL/2009/01 - Site Formation for Kai Tak Cruise Terminal Development

  • MTR Property Development at TW7, Tsuen Wan West Station, TWTL 403 (City Point) for Cheung Kong & Nan Fung

  • WSD Contract No. 1/WSD/09(E) - Term Contract for Waterworks - District E - New Territories East

  • Residential Development (Package 3) at TKOTL 70, Area 86, Site E, Tseung Kwan O (HEMERA) for MTR & Cheung Kong

  • DSD Contract No. DC/2009/07 - North District & Tolo Harbour Regional Sewerage - Upgrading of Trunk Sewers at Ma Liu Shui, Tai Po & North District

  • CEDD Contract No. TK/2009/01 - Infrastructure Works at Town Centre South & Tiu Keng Leng, Tseung Kwan O

  • MTR Express Rail Link Contract No. 822: Tse Uk Tsuen to Shek Yam Tunnels

  • MTR Express Rail Link Contract No. 821: Shek Yam to Mei Lai Road Tunnels

  • Contract No. 1016EM10 - Chilled Water Pipe Laying Works at North Apron Area for District Cooling System at Kai Tak Development

  • DSD Contract No. DC/2007/12 - Design & Construction of Tsuen Wan Drainage Tunnel

  • DSD Contract No. DC/2007/10 - Design & Construction of Hong Kong West Drainage Tunnel

  • MTR Contract No. K0736-11C: New Entrance & Concourse at University Station

  • Hong Kong Disneyland Resort Project GC-12 - Grizzly Gulch

  • DSD Contract No. DC/2008/02 - Improvement of Fuk Man Road Nullah in Sai Kung

  • ArchSD Contract No. SS S328 - Expansion of Tseung Kwan O Hospital

  • DSD Contract No. DC/2007/19 - Drainage Improvement in Northern H.K. Island - Western Lower Catchment Works

  • CEDD Contract No. KL/2008/07 - Kai Tak Development - Stage 1 Advance Infrastructure Works for Developments at the Southern Part of the Former Runway

  • Superstructure Works for Proposed Residential Development at 13-27 Warren Street, Tai Hang (WarrenWoods)

  • Hennessy Centre Redevelopment at 500 Hennessy Road, Causeway Bay (Hysan Place) for Hysan

  • CEDD Contract No. HK12/02 - Central Reclamation Phase III Main Works

  • The Hong Kong Polytechnic University Phase 8 Development

  • ArchSD Contract No. SS P318 - Design & Construction of Tamar Development Project

  • ...and so forth.

Hydrotite is a trademark and a brand of C.I. Kasei Co., Ltd.  C.I. Kasei Co., Ltd. (established in 1963) has merged with Takiron Co., Ltd. (established in 1919) on April 2017 to become C.I. Takiron Corporation.  As a result of the merger, C.I. Takiron expanded and deepened its business areas to include the following: 1) construction materials business such as housing equipment and building materials, floor materials, and building decoration materials; 2) environmental materials business such as agricultural materials and civil engineering materials; 3) high functional materials business such as industrial plates and electronic components; and 4) specialty films business such as heat-shrinkable film for packaging and packaging materials.